June 2015 – KTL win Dersalloch Wind Farm 132kV OHL Project with Scottish Power

KTL was been awarded a project to design and construct an Overhead Line for Dersalloch Wind Farm in South Ayrshire as part of the SWS (South West Scotland) Windfarm connections for Scottish Power. These connections also include New Cumnock – Margree, New Cumnock - Dunhill – Blackhill, Blackhill - Glenglass Hill, Dun Hill.

The project is to Design & Construct a new 6.2km 132kV Single Circuit, 4 Wire Heavy Duty Wood Pole (HDWP) overhead line between the new proposed 132Kv Windfarm substation at Dersalloch and the new 275/132kV substation at New Cumnock. Conductors are 200mm2 AAAC (Poplar) Conductors and underslung OPGW (Horse equivalent) 70mm2 AACSR/ACS.

A number of distribution (LV) overhead line crossings will also need to be moved underground prior to the works taking place.

Home About News June 2015 – KTL win Dersalloch Wind Farm 132kV OHL Project with Scottish Power

Head Office

Killarney Telecommunications Limited.
Unit P, M7 Business Park,
Newhall, Naas,
Co. Kildare,
Ireland.
Company Number: 280010

Office - UK

KTL
Unit 5, Denbigh Hall Industrial Estate, 
Bletchley,
Milton Keynes,
MK3 7QT

UK 

 

ISO Certified in Ireland